WITHERNSEA IN PICTURES

Withernsea Pier and Promenade Association News

News Update April 2021

Having successfully raised the necessary funding for the project earlier this year, work was due to start on the Withernsea Pier viewing platform on March 29th. Unfortunately, this has not been able to go forward, as last month East Riding of Yorkshire Council raised a number of additional questions on the plans submitted for planning, and approved in May 2019. This list of queries has been forwarded to the architects and engineers involved, who will, it is hoped, clarify in the coming weeks the points highlighted by the council.

However, the delay has had implications for the proposed cost of the project. The pandemic has naturally slowed down all communication and decision making processes with third parties, and this delay is now having an impact on the fixed price quote of 2019. We await a new quote from the construction company, but we are led to believe that there will be a considerable increase in costs. Until we receive an updated figure for the construction, and have the information to provide a satisfactory response to the Council’s technical questions, we are unable to commence the preliminary work on the viewing platform.

Disappointing as this is to all who have been so supportive of this vision, we only see this as a deferment to the start of the work. However, the prospect of increased costs will mean that the fund raising era is not yet quite over. Be assured that the committee of the Withernsea Pier and Promenade Association will endeavour to do all that they can to get the project back on track as soon as possible.

On a more positive note, There will be a programme, called ‘Walking the Plank’, about the Withernsea pier project on BBC Radio 4 on Monday 19th April at 8pm and repeated Wednesday 21st April at 11am. It will then be on BBC Sounds. Further good news, the Withernsea Pier Towers and the Coastal Change Observatory will be opening for the new season on Saturday, April 17th.

Planning approval for Viewing Platfrom

 

News Update March 2021

We are still working with East Riding Council to resolve any outstanding issues with the building and lease agreement to enable them to give us landlord consent for the build.
This will involve at least a week’s work by our design engineer at Alan Wood to adress the latest 67 questions and queries about the drawings.
There are still other issues like street licencing that need to be resolved. We cannot get a building and lease agreement until all issues have been resolved with the council.

Without the building and lease agreement, we have been unable to sign the fixed price construction contract with our main contractor, UKI. Without a signed contract, we were unable to make the first payment for ordering materials which was due by the end of February. Due to the delays, UKI have put all ordering of materials for the build on hold for now.

The original quote for construction from UKI was from October 2019. They have now informed us they are unable to hold the price at the original quote, due to increasing cost of materials and increased costs from subcontractors. The WPPA are awaiting a new quote, and will evaluate the situation once the new cost for construction has been determined.

 

 

News Update January 2021

WITHERNSEA PIER STAGE 1 NOW FULLY FUNDED, CONSTRUCTION START IS IMMINENT

Following a grant offer of £125,000 from Withernsea Big Local almost exactly a year ago, The Withernsea Pier and Promenade Association have been working hard to secure the rest of the funding to build the first stage of the new Withernsea Pier.
Sales from the newly opened Pier Towers souvenirs shop, along with selling commemorative plaques and some very generous donations from the public have got us to within £25,000 of being able to start construction.
Withernsea Big Local have just informed us they are increasing their grant offer to £150,000 with an additional £10,000 as a contingency. Along with a grant from the East Coast Communities fund, donations, and our own fundraising, the first stage of construction, the Viewing Platform, is now fully funded.
Withernsea Big Local is one of 150 areas across England each awarded £1m over a 10-year period, to develop resident-led investment programmes to achieve lasting change. Big Local funding originated from the National Lottery and is administered by a Local Trust. The award was made under the local Investing in Withernsea Programme which started in 2015 and which has supported the Pier project from the outset.
The Pier Association went out to competitive tender for construction of the Viewing Platform in 2019. We are pleased to announce that our main contractor will be UK Industrial Services (UKI) based near Manchester. UKI has the experience and capabilities to deliver marine and coastal engineering works across the UK. They have an in-house team of specialists who deliver world-class solutions in these environments.
A Marine Licence and Planning Approval for the construction have already been obtained. We have agreed heads of terms for a lease agreement with East Riding of Yorkshire Council for the land, and are just waiting for them to produce the final lease agreement. With the funding now in place, we hope to start the construction work by the end of March, with the Viewing Platform being opened to the public ready for this summer season.

Withernsea Big Local

 

News Update November 2020

2020 has been an eventful year despite all events being cancelled. Even though the first lockdown forced us to cancel the planned opening ceremony of the Pier Towers in the Spring, work still carried on with fundraising and admin work behind the scenes.

We have installed two bench seats outside the Towers, one kindly donated by Lisa Dawson, and the other by the Withernsea Lions. Visitors can sit and relax and look along the length of the Promenade, a delightful spot on a sunny day! Thanks to funding from the Yorkshire Coast Bid, we now have eco-friendly colour changing LED floodlights to illuminate the Towers. During the dark winter nights these enhance this landmark for visitors and locals alike. The next step will be to secure funding for solar arrays on the roof to provide clean energy.

With the help of fantastic volunteers we were able to open the Pier Towers for trade from June 15th every day till October. During October we were still open every weekend, and visitors were able to come in and see the array of souvenirs available, as well as all the different displays. The South Tower also had three stalls open for different local vendors throughout, as well as a further two stalls outside. Sadly we have now closed the Towers completely due to Lockdown 2, but will open again next year.

Two recent very generous donations of £10,000 each have pushed us over the £200,000 mark in raising the necessary funds for the build of the first stage of the Pier, and we now only need another £41,000 to start construction. All required permissions have been granted, so if we can secure the rest of the funding, we aim to start construction in March and plan to open ready for next summer season.

The WPPA would like to thank all our members, volunteers, stall holders and visitors for their support in 2020 and welcome everyone back in 2021.

Stalls at Pier Towers Withernsea 2020

 

 

News Update July 2020

Pier Towers Open July 2020

Pier Towers, the gateway to the original Withernsea Pier, are now open seven days a week from 10am to 4pm until the end of the summer season. There is lots to see inside:

- Plans for the new Withernsea Pier
- Coastal change display looking at our ever-changing coastline, coastal erosion and sea defences
- Windmills of Holderness
- Yorkshire Birdlife with bird spotting guide
- Walking Withernsea, 5 different routes to explore in and around Withernsea
- Historic Withernsea slide show, over 150 pictures of old Withernsea
- Picture gallery
- Arts and crafts stalls
- Souvenirs and postcards
- General Information about Withernsea and the surrounding area

As we are now finally able to start trading, we have registered for VAT. This means we can reclaim VAT on the construction costs. So the total cost of stage 1, the Viewing platform has just gone down from £300,000 to £250,000. Including provisional funding, we have £185,000 towards the construction cost, and now only need to get another £65,000 before we can start construction.

 

 

News Update June 2020

As part of the easing of lockdown restrictions, The Withernsea Pier and Promenade Association are pleased to announce that we will be opening up Pier Towers to the public from Monday 15th June. The reopening of the towers after many years of standing disused is an important step in the long-term plans to re build the Withernsea Pier, as the Towers were the gateway to the original pier completed in 1877.

We successfully applied for a grant from Yorkshire BID who have awarded us £3,879 to pay for 4 market stalls and two market carts depicted below. The funding also covers the costs of the coastal change exhibition which will be displayed in the north tower and floodlights to light up the towers at night. We are most grateful to Yorkshire BID for supporting this project.

Stalls are available to hire at an introductory offer of only £5 per day until the end of June, and these can be booked by completing our hire agreement, available to download here, and to email to us or drop off at pier towers when they are open. Bookings will be done on a first come first served basis. In order to maintain social distancing, a maximum of 3 people will be allowed in each tower at any one time.

Pier Towers Stalls

 

 

News Update March 2020

We now have a 99 Year Lease of Pier Towers and we have Planning approval to Use Pier Towers to form an exhibition area with tourist information, retail stalls and associated public seating and installation of replacement flood lights and roof-mounted solar panels. This is a major milestone as we can now bring this iconic Withernsea landmak back into use.

Sadly due to the current Corona virus situation, the grand Easter Opening Event will have to be postponed until further notice. We will continue to get things ready as best we can and the opening of the Towers will take place as soon as it's safe to do so.

 

 

News Update January 2020

WPPA receive cheque for £125,000 from Withernsea Big Local

The Withernsea Pier and Promenade Association is delighted to announce that we have received a grant offer of £125,000 from Withernsea Big Local towards the construction of the first stage of the Withernsea Pier, the Viewing Platform. Withernsea Big Local is one of 150 areas across England each awarded £1m over a 10-year period, to develop resident led investment programmes to achieve lasting change. Big Local funding originated from the National Lottery and is administered by Local Trust. The award was made under the local Investing in Withernsea Programme which started in 2015, and which has supported the Pier project from the outset.

The Pier Association went out to competitive tender for construction of the Viewing Platform in 2019. We have establishing that the total cost of constructing will be just under £300,000. With a grant from the Harold Bowler Foundation, funding from Withernsea Town Council, funding from Ørsted’s East Coast Community Fund, the new funding from Withernsea Big Local and funds from our own fundraising activities, the total funds raised now stands at £185,000. This means we only need another £115,000 to build the first stage of the Pier.

Withernsea Big Local

Significant progress has been made with Pier Towers, the gateway to the original Withernsea Pier. The Pier Association finally obtained a long-term lease agreement form East Riding Council this January after nearly 12 months of negotiations. We have recently submitted a Change of Use Planning Application to bring the Pier Towers back into use, which will then enable us to further promote the building of the Pier.

Plan for Withernsea Pier Towers

We will have three market stalls in the South tower, supplemented with three further pop-up stalls outside providing an outlet for local crafts and interested businesses. Anyone can hire these stalls on a daily or weekly basis. If you are interested in a stall, please fill in an expression of interest form which can be found here.

The North tower will be an exhibition space housing permanent and temporary displays:
It will feature a Coastal Change Observatory looking at the ever-changing coast, coastal erosion, impact of sea defences, long shore drift, the formation of Spurn Point and the Lost Villages of Holderness.
A renewable energy display will promote the use of renewable energy, such as wind, solar power, tidal and wave power with links to our local offshore windfarms. The towers will also be used for tourist information and exhibitions on local history, wildlife and displays from other local groups and organisations.

We will be holding an opening event over the 2020 Easter Weekend. There will be live music and entertainment with an opening ceremony of the Pier Towers taking place on Sunday 12th April at 6.00pm.

 

 

News Update October 2019

Some great news: The provisional funding from the East Coast Communities Fund which was due to expire on the 4th October has now been extended until March 2020. This gives the WPPA some extra time to find match funding from other sources. We have recently applied to the National Lottery Heritage Fund and also submitted an application to Power To Change. RDPE have confirmed they will have another round of funding, and we will be resubmitting our bid to them when that round opens up shortly. Withernsea Big Local have also confirmed their commitment to the project stating that "The Pier project is of high importance to Withernsea, and we will contribute to enable the project to go ahead"

Local support is still strong for the project with new members signing up, new sponsors, and local groups and businesses helping with fundraising. The Withernsea Scarecrow Trail raised an amazing £400 for the pier. Well done to Kelly and her team for a great event, we hope it will be repeated next year. We would also like to thank the Withernsea branch of the RAOB for their generous donation of £200. The raffle for a 2 hour tattoo session donated by Martyn Wheal Tattooist raised £203. The winning ticket was Yellow 190 drawn at the Old Boat Shed on Thursday 10th October.

We had a positive meeting with East Riding of Yorkshire Council to discuss the lease of Pier Towers and are hopefull that the lease arrangements will be in place for us to open up the Pier Towers by Easter next year. If you are interested in having a stall at the towers please get in touch.

 

News Update August 2019

Unfortunately the RDPE (Rural Development Programme for England) did not approve our recent funding application. This would have been substantial in covering the cost of construction for the First Stage, the Viewing Platform leading out over the beach from the Pier Towers on the Promenade. This also means we will not receive the earlier match funding from the ECCF (East Coast Communities Fund) and associated promises of amounts to cover any funding shortfall.

Whilst this can be seen as a setback, it is worth noting we still have Planning Permission to build the first stage, the Marine Licence which allows us to construct out over the beach, as well as all the technical drawings, and the tenders so far received for construction, so it can be seen as a hurdle, but one which can be overcome with patience and measure. With the experiences of applying for funding, we will continue to explore other avenues, be it an individual Benefactor/Business willing to fund the project, or via further applications for funding. The majority of local businesses have supported the WPPA, but we also need the involvement of the large chain stores in the town as well. The Pier Project will benefit all businesses in the town.

Having gone out to tender, and obtained quotes for the construction, we are confident that the Viewing Platform can be achieved for about £300,000. Fundraising and planning for construction works still carry on, with a number of events planned, and renewed efforts to find a new main sponsor of the project. In order for us to succeed in delivering the Pier Project, which will complement existing attractions, and make Withernsea a noted destination for tourism, we do need to have more people on the Steering Group/Committee, more volunteers to assist with events, and the ERYC being a more enabling partner, along with support from big businesses.

We had a stall and tombola at the recent Withstok music festival and raised another £280 for the Pier Project.

 

News Update July 2019

Sponsored bike ride Dover to Oslo

Oliver and Benjamin setting off on their 1200mile sponsored bike ride from Dover to Oslo. Benjamin managed to cycle the full distance, while the rest of the family took it in turnes to cycle with him. We also reached our goal of raising £1,200 for the Pier. Thank you to everyone who showed their support by sponsoring us.

 

News Update June 2019

News update June 2019

It's been a good month for the Withernsea Pier and Promenade Association with us getting Planning Approval for the first stage of construction, and finally agreeing on the terms for the building and lease agreement with East Riding of Yorkshire council. Along with obtaining the Marine License in April, everything is now in place as far as permissions are concerned.

With our own funds along with a provisional grant of £38,618 from Ørsted’s East Coast Community Fund, £6,000 from the Harold Bowler Foundation and £3,500 from Withernsea Town Council we have reached the required match funding needed to apply for a grant from the Rural Development Program for England. The full application for approximately £180,000 was submitted end of May. We now have a six to eight week wait to see if our application is successful.

Hodson Architects and Alan Wood & Partners have completed the detailed design work and drawings for construction of the Viewing Platform. We had to make some changes to the substructure to make sure the platform would be structually stable in the harsh winter weather. The construction work is currently out to tender. If we obtain the necessary funding, the contracts will be awarded in July with a plan to start construction in September or October this year.

 

News Update May 2019

Pier Towers Refurbishment Withernsea

Refurbishment of the Pier Towers is now nearing completion. The damaged windowsills have all been replaced, broken windows repaired, and the leaking roof has been fixed. Some of the pointing between the bricks was in a very poor state, and is being repointed using a suitable lime-based mortar. The insides have also been refurbished with newly painted walls and new lino flooring to replace the old carpet tiles.
The scaffolding will be coming down middle of May, and the work is due to be completed by the end of the month.

Once completed, the towers will be transferred over from ERYC to the WPPA as a community asset. We are looking forward to bringing the towers back into use after many years of standing empty. We are planning to have a history display of Withernsea showing what the town looked like in the past including the original Withernsea Pier. There will also be a display showing our plans for the new pier. In addition, there will be information about renewable energy, use of solar and wind power and the impact of the large wind turbines seen on the horizon. We will have information about local attractions and general information for tourists.

There will be an opportunity for local traders to use the towers, and eventually the Viewing Platform for pop up stalls throughout the tourist season. If you are interested in this opportunity, please download our Expression of interest form and return it to the Pier Association.

 


News Update April 2019

Fundraising for the Withernsea Pier has just received a major boost from Ørsted’s East Coast Community Fund. The Pier Association (WPPA) applied for funding in January and have just been provisionally awarded a grant of £38,618 towards building the first stage which will be a large viewing platform extending out from the Pier Towers.

Pier Viewing Platform

The WPPA are delighted that the funders have found our project worthy. We have been working on this project for over three years, raising just over £31,000 so far. This means that a grant from Ørsted’s East Coast Community Fund would more than double our total funds raised to date to nearly £70,000. It’s a fantastic boost to everyone at the Withernsea Pier and Promenade Association who are working so hard for this, and all our volunteers and sponsors who are supporting our project.

So far, we have spent most of the money raised on various reports and studies, licensing fees, planning fees, architect and design engineer fees. The grant from Ørsted’s Community Fund will go towards the actual construction costs.

To cover the rest of the construction costs, the WPPA have applied for £185,000 from the Rural Development Program for England. We are at stage two of the application process and are progressing well in satisfying all the requirements of the funders. One of the major requirements was that we have at least 20% of the estimated £225,000 needed for construction. The grant from Ørsted’s Community Fund has brought us a lot closer, and we are now only about £3,500 short of achieving this goal.

WPPA Funding Bar

We are progressing well with all the other pre-construction requirements. The Marine Licence was issued on the 15/4/2019 and is one of the main requirements for the project. The planning application is moving forward and is now out for consultation and an agreement has been reached with East Riding of Yorkshire Council on the building and lease of the land.

This should put us in a very good position, and if we get the remaining funding we are applying for, we will be starting construction this September with an aim to be open to the public next summer.

If you would like to support us, please download our sponsor pack from our funding page.

 

 

News Update November 2018

Pier Fundraising events 2018

A number of fundraising events have taken place this autumn. We had a live concert at the Golf Club, one at The Northfield and one at the Ozone Club. All three events featured great artists who performed free of charge to help raise over £600 for the pier. Andrea Burns and friends put on a Halloween Evening at the Northfield, and the Pier Hotel arranged a Pier Spooktacular event which raised an impressive £947.
Total funds raised for the WPPA as of 6th November 2018 now stands at £20,203.

At the end of October, we submitted our application to the Marine Management Organisation for a Marine Licence. This is one of the requirements to enable us to build on land which is in the sea at high tide.
We are also making progress towards a building agreement and lease with East Riding Council with a draft version now being considered.

Planning permission is also progressing well with our flood risk assessment done and an impact report nearly completed.

The WPPA have put in a bid to the Coastal Revival Fund to pay for a structural engineer and architect to develop technical drawings and costings to stage 4 of RIBA plan of works. This work will enable the WPPA to be ready for construction when sufficient funds have been obtained. We are still waiting for a decision to our application.

We applied to the Coastal Communities Fund Round 5 for funding for the first stage of the Pier. Unfortunately, this has been unsuccessful due to the high level of competition. This year the Fund received a total of 285 Stage 1 applications worth £246 million; however, they only had a budget of approximately £40 million to spend.

We submitted an expression of interest to the Rural Development Program for England (RDPE) early in 2018. Our EOI was endorsed and we were invited to submit a full application for funding for the first stage of the Withernsea Pier. The full application has a number of tough requirements, but if we succeed it will pay for most of the £200,000 cost of the first stage. One of the biggest hurdles is that we have to have at least 20% match funding which is £40,000 so we need to find a large sponsor quickly. Even if we don’t meet the requirements for funding this time round, we are steadily working through all the requirements so that we will be ready for the next round of funding.

 

 

 

News Update September 2018

Victorian Bathing Huts and Ruby Reds

We had a stall at the 3 day Withfest event. There was a lot of interest in our Pier Project and Victorian Bathing Machines which were used to display our sponsors and the latest plans and drawings of the pier. We also had a tombola and raised over £200 for the Pier.

Ruby Reds concluded their Bring Back Our Pier tour with a fabulous show at the Northfield and presented the WPPA with a cheque for £1,601.80p. A great result thanks to all the hard work by the Ruby Reds.

We received a reply from East Riding Planning office to our pre-planning enquiry in August. The main requirements were for us to:
- Consider the impact on coastal processes and maintenance of existing coastal defences
- Apply for Marine licence from the MMO
- Submit a flood risk assessment
The reply concludes that the proposed pier plans could be supported subject to the above matters being addressed. It will obviously still have to go through the full planning application process.

A proposed building agreement and lease was received from ERYC on the 16th August 2018. Some points need clarifying and further discussions will be held to come to a final agreement. The proposed agreement will assist us to secure the necessary funding for stage 1.

The summer was also a good time to bring on more sponsors and new members. The total now stands at 105 Sponsors and 106 members.
All our sponsors are listed on our sponsors page.

We have a number of events booked for this autumn. All events are free.
Friday 14th September 8.00pm Music Concert at Withernsea Golf Club with James Danby, Work in progress and Ric & Lou's loudhailer.
Friday 28th September Music Concert at the Northfield with Stuart Dainty, Carry Martin and The larks.
Friday 26th October Live music at the Ozone Club with Helen & Nick Stubbs and the Aldborough Cowboys.
Saturday 3rd November Halloween evening at the Northfield by Andrea Burns & Alison.
For more information please visit our Facebook page.

 

 

News Update June 2018

Pier Aerial View 2018

Architect Robert Blundell from 3xa Design has produced some faboulus drawings of our new pier. We will use these drawings when we submit our pre-planning application to ERYC this week.

The Ruby Reds are doing a great job raising money for the Pier with their Bring back our Pier Tour. They have already had sucessfull performances in Withernsea, Keyingham and Sproatley. Next shows are:
Friday 29th June 7.30pm at Cleveland Club in Hull
Saturday 30th June 7pm Skipsea Village Hall
Friday 6th July at Khardomah 94 in Hull
Friday 13th July 7.30pm at the Floral Hall in Hornsea

We attended the official Withernsea Pavement Fountain opening event in May and will be at Withfest from the 3rd to 5th of August. Look out for our Victorian Bathing Machines and come over to have a chat and see our latest plans.

 

News Update April 2018

WPPA News Update April 2018

Our recent Comedy Night at Shores was a sell-out success, raising over £200 towards the Withernsea Pier Fund. We also had our first free concert at Captain Williams raising another £133.

WPPA are pleased to announce that we have teamed up with the Ruby Reds who will be raising funds for the Withernsea Pier on their Bring back our Pier tour 2018. First event will be at the Boating Club in Withernsea on the 25th May, second event in Keyingham Village Hall on the 8th June. Lots of more dates and venues to follow.

We held our AGM at the Meridian Centre on the 12th of April. The Chairman introduced the Committee, and then gave a presentation via Powerpoint of the Withernsea Pier And Promenade Association over the past year, the process of building in Stages, and the cost of each stage and our publicity and fundraising strategy. This was followed by a Q&A session. The current comittee members were unanimously reelected.

 

News Update December 2017

WPPA Fundraising 2017

The Fundraising concert was a great success raising £558.20 for the WPPA. We had a stall at the WRCG Fireworks event. Despite the bad weather we managed to raise £60. We also attended the Christmas Light Switch On. There was a lot of support for our plans, and our tombola raised a further £131.39.

 

News Update September 2017

Concert

The ongoing fundraising in Withernsea is going well. We are getting new sponsors, new members and selling tickets to our fundraising concert on the 26th October. If you haven’t yet got your tickets, you can get them from The Northfield, Carousel on Queen Street or the Shores Centre on Seaside road.
We have updated our sponsorship pack which is a short document summarizing our plans for the pier, along with a sponsorship form. You can download a copy here. We are also starting to preparing our applications for the large funding sources. We now have an extensive list of possible funding sources for us to consider. One of our targets will be the Coastal Communities Fund. The 5th round of funding will open for applications early 2018 and we have a lot of work to do to be ready for it.

 

 

News Update June 2017

Following last month’s appeal in the Gazette for pictures of the Pier Towers, The WPPA are grateful to Mark Dawson for the pictures he has given us of Pier Towers before and during the construction of the steps. We would also like to thank councillor Lyn Healing and ERYC Planning Department for providing us with plans of the construction of the steps. This information will assist us in designing the first stage of the new Withernsea Pier.
We are in dialogue with East Riding of Yorkshire Council, the Environment Agency and a number of other consultees to determine what reports, surveys and consultations we need to undertake for the Withernsea Pier. It would appear from the response so far that there are no major hurdles to building the first stage if we can raise the £200,000 needed for construction.

Our plan for fundraising is to gain maximum support from residents and local businesses, and then use that momentum to apply for larger amounts of funding from bigger organisations. See our sponsorship page for a list of our sponsors so far.

 

News Update April 2017

The Feasibility Study, funded by Withernsea Big Local has now been done, and the report received. In layman’s terms, the result is that to rebuild a Pier at Withernsea IS feasible. So we have the green light to go ahead and concentrate on funding construction. There is still an amount of work to be done on research (foundations, piling types, coastal effects), but the Pier is now one step closer to being built!

We have used the donation from Tesco to print leaflets and make Pin badges, which will be used to raise awareness at events in the Town. Two large “pop-up” banners highlighting the Pier Project have been funded by a private sponsor, which will be used at events to attract interest and detail explanations of the project and why it is important.

We will be attending The Great British Coast National Conference and promoting our project.
Plans are afoot to use the Pier Towers, with the permission of ERYC, to promote the Pier project at events this summer.

A Request for Screening and Scoping Opinion has been sent to ERYC to clarify what enironmental studys etc we need to undertake.

 

News Update February 2017

After funding was secured for a Feasibility Study (from BigLocal), invitations to tender were sent out to eight interested firms. Following the closing date for tenders, the replies were evaluated thoroughly at the January 12th meeting of the WPPA, and reduced to a shortlist of two. After replies had been received to a number of queries on both Tenders, a further meeting was held on January 27th, and the decision was made to award the work to A&F Consulting Engineers LPP.
A Steering Group Meeting and site visit was held on Friday February 3rd.
This is a real milestone for the initial phase of the project!

The primary objectives of the study are to:
- Evaluate the proposed construction and suggest any suitable construction options.
- Identify any further studies that may be required and the possible cost implications.
Specify which of these are needed for Stage One, and for the whole project.
- To determine a rough cost of each of the four stages of construction.
- Provide a step by step plan to complete Stage One.
The final report is expected middle of March 2017.

Funding has also been received from the local Tesco’s, which will be used to help produce badges and leaflets to further the promotion of the project, and get word out and create more interest. A presentation was made by both the Service Manager and Community Champion with five of the WPPA members, and the Gazette Photographer was on hand to record the event. This was published in the Gazette of February 2nd 2017.

The application to register as a charity was turned down by the Charities Commission, the project did not meet their criteria. Discussions about the future of the WPPA could include the WPPA becoming a CIC (Community Interest Company) Meanwhile, the WPPA has now been registered as a Company, Limited By Guarantee, and registered at Company’s House.

The WPPA Bank Account is all set up, with monies paid in, hopefully more to follow through fundraising events in the future and donations/grants.

The position of Vice-Chairman, which had become vacant, has been filled by D Edwards. Richard Harries, recently joined, has been seconded to assist the News and Media position.

Our Business Plan is being drafted and updated

 

 

News Update December 2016

Withernsea Big Local

We are pleased to announce that our application for funding from Withernsea Big Local has been approved. WBL have agreed to fund a feasibility study for the Pier. It will verify our plan, give us a better idea of costs, and determine if our goals are achievable.

 

News Update November 2016

We are in the process of crafting a consultant brief, to be presented to businesses that can carry out a feasibility study. We have been liaising with East Riding, Withernsea Big Local, and multiple engineering companies while we put it together.

 

News Update September 2016

WPPA are grateful to have secured £200 of funding from the local Tesco store in Withernsea, for the production of leaflets and stickers to promote the group and our objectives.

 

THE MERMAID RETURNS
A mermaid tale by Richard Harris

 

Media coverage

Media coverage is now on a new page. You can find it here.

Withernsea Pier and Promenade Association Ltd. 2 High Brighton Street, Withernsea HU19 2HL. Registered in England. Company number 10593143